October 14, 1997
An integrated current of 5.6 A*hrs was gained during 8:39 AM (Oct. 13) and 8:57 AM (Oct. 14). Average beam current during this period was 232 mA.
Linac study was carried out in the daytime (9:00 AM - 4:39 PM).
In the evening, an orbit feedback system was tested. Tuning on the beam optics (correction of optical functions) was also carried out. After these works, vacuum conditioning continued (after 1:29 AM, Oct. 15).
Beam current and beam lifetime in this morning.
Linac study is under way.